Kuali Phase I – (Proposal Development and COI)
  • Outreach & Awareness (Sept 2015 – Apr 2016) √  Complete
  • Develop Project Plan (Dec 2015 – Apr 2016) √ Complete
  • Phase I Implementation Project  (Apr 2016 – Oct 2017) √ Complete
  • Phase I in Production (Oct 2017 – March 2018) Now In Progress 
  • Phase I Project Closeout/Review (Jan 2018 – March 2018 )
Kuali Phase II – (Award, Negotiation, SubAwards, Reporting, Compliance (IRB  & IACUC)
  • Award Project Kickoff (Nov 2017) √ Complete
  • Develop Award Project Plan (Nov 2017 – Dec 2017) √ Complete
  • Award Implementation & Pilots (Jan 2018 – Feb 2018) Now In Progress 
  • Other Phases  (TBD)