Hi Campus Community

Exciting news about Kuali Research!

We are finalizing the configurations Phase 1 of Proposal Development.

We are currently reviewing the final configuration decisions and designs ( in the Kuali System) and beginning to construct training documents for the Proposal Development module ( based off the final configurations) Our projected timeline for the next month is as follows:

  • 5/1 – 5/12: report development/testing
  • 5/15 – 5/26: final UAT and approval
  • 5/29 – 6/2: buffer week
  • 6/5 – 6/9: system live; pilot begins
  • 6/12 – 6/30: pilots, immediate post go-live support

*Updated May 26th 2017*

 